Location:
Delaware Basin, Texas
Fuel supply:
Natural gas pipeline
Turbine installation time:
1 day
Reliability:
99+% mechanical uptime to date

Requirements: Customer required an alternative diesel generator solution to avoid the logistical hassle of diesel fuel delivery and multiple generators strewn across a very remote 13 well SWD facility. Natural gas generators were not an option due to lack of a gas supply at the individual locations.

Solution: Two 5.7 MW SMT-60 gas turbines provided power to the entire facility via the customer installed overhead power lines. LCP matched the line voltage to the customer’s requirements.